Project Details
The project consisted of the excavation of 93,630m3 of silty sand within Port Stanley Harbour to reduce instances of flooding along Kettle Creek. Open-water disposal sites were located 3km and 6km from the harbour entrance. All dredging was conducted utilizing Dean’s GPS-positioned hydraulic excavator. Open-water disposal was performed with Dean tugs and 600m3 dump-scows.
Turbidity monitoring was conducted at the dredge site and in Lake Erie, as the dump-sites were upstream from the municipality’s water intake. No shut downs due to turbidity exceedances were triggered. As a result of Dean’s aggressive pricing and Dean’s early completion of the original contract quantity, the Owner elected to increase the dredge quantity from the original 88,000m3.
Port Stanley Harbour Being Dredged By Dean Construction
Owner Information
Owner
Municipality of Central Elgin
Contact Person
Aaron Dooling
Phone
519-631-4860
Consultant Information
Consultant
Riggs Associated Ltd.
Contact Person
Jill Coles
Phone
519-657-1040